Art Installation at Tremblay Station

Project Update – Alignment

Final clean-up at all stations continues. Alstom is running coupled trains on the guideway.

Train Testing at Cyrville Station

Testing Program and Outstanding Items

 The testing program continues to address the following final items:

    • Train vehicle preparedness and reliability continues to improve and is tracked daily
    • Final testing of the control systems for transit operations

Upcoming Activities

Once substantial completion of the project has been achieved, the following activities are scheduled to occur:

  • Trial running
  • Safety Auditor sign-off