Construction Update

Station Tremblay Station

Project Update – Alignment

OC Transpo is running daily practice plans on the guideway. Fencing and hoarding has been removed and final clean-up at all stations continues.

Entrance to uOttawa Station

Testing Program and Outstanding Items

The testing program team continues to address the following final items:

  • Train vehicle preparedness and reliability.
  • Additional Tunnel Ventilation System (TVS) tests.
  • Final testing of the control systems for transit operations

Once substantial completion of the project is achieved, the following activities are scheduled to occur:

  • Trial running
  • Safety Auditor sign-off