Construction Update

Station Bayview Station

Construction on the Confederation Line nears completion and RTG is actively working toward finishing remaining works and the testing and commissioning program.

Station Bayview Station

Construction Update – Alignment

Occupancy permits have been issued for all stations. Final clean-up at all stations is underway.

Art installation at Tremblay Station is underway.

Station Tunney's Pasture Station

Testing Program

The testing program and team is addressing the following final items:

  • Full train vehicle availability and reliability
  • Testing of the train control system
  • Ensuring that the train operating system is complete
  • Final testing of the control systems for transit operations
  • Final testing of the power system for the alignment and trains
  • Maintenance readiness

Upcoming Activities

Once substantial completion has been achieved, the following activities are scheduled to occur:

  • Trial running
  • Safety Auditor sign-off